Beijing Development Area( BDA) renewable water plant put into use

2008-07-21

July 20, the first Phase of China first renewable water plant which main customer is microelectronics industry ¨C BDA renewable water plant project completed and put into use, then start to supply water to the Nokia (China) Investment Co., Ltd., SMIC Manufacturing (Beijing) Co., Ltd. and other 20 enterprises. According to statistics, BDA production and daily living water supply is about 55,000 tons. Along with the completion of Renewable water plant project, 15,000 to 20,000 tons high-quality renewable water can be produced everyday. After Phase II of the project is completed, daily water production will reach 35,000 to 40,000 tons. Gradually reach the target that renewable water supply will reach 60% of total BDA water supply.  Then renewable water will become main supply water of BDA.

 

 


 
    
¡¾Close¡¿